露天煤矿倾斜软弱基底排土场边坡煤柱留设宽度研究

Coal pillar retention width for dump slopes under inclined weak foundation in open-pit coal mines

  • 摘要: 露天煤矿开采过程中,留设煤柱是改善排土场边坡稳定性的重要手段。现有针对煤柱留设宽度确定方面的研究多基于理论分析、应力分布及塑性区演化特征,对倾斜软弱基底赋存条件下边坡滑坡模式考虑不足,确定煤柱留设宽度时没有兼顾安全性与经济性。以国能新疆准东能源有限责任公司准东露天煤矿二采区东帮排土场为工程背景,采用数值模拟方法,分析了排土场边坡的位移及最大剪应变增量变化特征:排土场边坡剪切变形主要集中于底板弱层及坡脚区域,潜在滑移面沿底板弱层发育并趋于贯通。由此确定了排土场边坡在倾斜软弱基底赋存条件下的2类潜在滑坡模式——受底板弱层控制的整体滑动和受煤柱留设宽度影响的局部滑动。结合2类潜在滑坡模式开展了不同煤柱留设宽度下边坡稳定性分析,通过扩大煤柱台阶宽度和运输平盘宽度分别提升排土场边坡局部稳定性和整体稳定性,确定了不同煤柱留设宽度下的边坡安全形态;在此基础上,计算煤炭损失费用和二次剥离费用,发现随着煤柱留设宽度的增加,煤炭损失与二次剥离的总费用呈先降低后升高的变化趋势。按照“先安全稳定、后经济合理”的原则,确定了排土场边坡煤柱合理留设宽度在40~80 m时,既可满足边坡稳定性要求,又能兼顾经济效益。

     

    Abstract: During open-pit coal mining, coal pillar retention is an important measure to improve the stability of dump slopes. Existing studies on the determination of coal pillar retention width are mostly based on theoretical analysis, stress distribution, and plastic zone evolution characteristics, with insufficient consideration given to slope failure modes under inclined weak foundation conditions, and both safety and economy have not been simultaneously considered in determining the coal pillar retention width. Taking the east dump slope in the second mining area of Zhundong Open-Pit Mine of CHN Energy Xinjiang Zhundong Energy Co., Ltd. as the engineering background, numerical simulation methods were adopted to analyze the displacement and maximum shear strain increment characteristics of the dump slope. The results showed that the shear deformation of the dump slope was mainly concentrated in the weak floor layer and the slope toe area, and the potential slip surface developed along the weak floor layer and tended to become continuous. Based on these findings, two types of potential slope failure modes of the dump slope under inclined weak foundation conditions were identified, including overall sliding controlled by the weak floor layer and local sliding affected by the coal pillar retention width. Stability analyses of the slope under different coal pillar retention widths were then carried out based on the two potential slope failure modes. The local stability and overall stability of the dump slope were improved by enlarging the coal pillar bench width and haulage berm width, respectively, and the safe slope configurations under different coal pillar retention widths were determined. On this basis, the coal loss cost and secondary stripping cost were calculated. It was found that, with the increase in coal pillar retention width, the total cost of coal loss and secondary stripping first decreased and then increased. According to the principle of "safety and stability first, followed by economic rationality", the reasonable coal pillar retention width for the dump slope was determined to be 40–80 m, which not only satisfied the slope stability requirements but also achieved favorable economic benefits.

     

/

返回文章
返回